EVNGENCO1's plants basically operate stably, meeting the system's mobilization needs

EVNGENCO1's plants basically operate stably, meeting the system's mobilization needs

In January 2024, EVNGENCO1 produced 2.42 billion kWh, reaching 93.6% of the planned output assigned by the Ministry of Industry and Trade.

The frequency of water returning to EVNGENCO1's hydropower reservoirs is generally good, closely following the plan of the Ministry of Industry and Trade. In addition, the Corporation also strives to supply fuel to thermal power plants to meet operating needs and maintain a reserve volume higher than the minimum norm; Maintenance and repair work ensures on schedule and quality according to plan.

Maintenance and repair of power units ensure on schedule and quality

Regarding construction investment, construction investment projects are being implemented by the Corporation according to the assigned schedule. Other activities such as digital transformation continue to be actively implemented by EVNGENCO1 with the goal of becoming a digital enterprise by 2025; Environmental protection is emphasized and many strict and effective measures are implemented.

On the occasion of Lunar New Year 2024, EVNGENCO1 and its units have implemented many social security activities in their operating areas, with a focus on gift giving and support programs for people in difficult circumstances. Celebrate Tet warmly and fully, demonstrating EVNGENCO1's social responsibility to the community.

EVNGENCO1 and local authorities hand over the Great Solidarity House and give gifts to families in difficult circumstances in Ninh Thuan province before the new year

In parallel with social security activities, EVNGENCO1 Trade Union, with its expertise, has organized activities to care for the lives of employees throughout the Corporation, especially visiting and encouraging employees on duty to celebrate Tet at homes. machine.

In February 2024, EVNGENCO1 focuses heavily on ensuring safe and efficient operation of the plants, completing the assigned electricity output of 1.67 billion kWh. In particular, EVNGENCO1 has issued a Directive on implementing solutions to ensure electricity supply in 2024 and the following years. In particular, thermal power plants ensure availability, reliability, and maintain good coal reserves; Hydropower plants comply with the Inter-Reservoir Operation Procedure, ensuring safety, efficiency, savings and optimization of water resources; Carry out maintenance and repair work according to plan.

Construction investment, digital transformation and other works will still be implemented by EVNGENCO1 as planned, maintaining sustainability and stability of production activities throughout the Corporation.